Hyderabad Metro Green Line Extension (MGBS - Chandrayangutta) Route Map, Stations & Status
The Hyderabad Metro Green Line Extension (MGBS to Chandrayangutta) is a 7.5 km elevated mass rapid transit corridor under implementation serving the historic Old City of Hyderabad across 6 stations: MGBS, Salarjung Museum, Charminar, Shalibanda, Falaknuma, and Chandrayangutta. Part of Phase II Corridor VI, the line extends Corridor II south from MGBS to Chandrayangutta, where it will interchange with the proposed Airport Corridor.
Want Your Brand Featured Here?
Reach thousands of decision-makers and investors searching for infrastructure projects every month.
Hyderabad Metro Green Line Extension (MGBS - Chandrayangutta) Economics
Expected Completion Date
Hyderabad Metro Green Line Extension (MGBS - Chandrayangutta) Stations
| # | Station | Type | Interchange / Connection | Opened |
|---|---|---|---|---|
| 01 | MGBS | Operational Interchange | Red Line I & Green Line II Operational Terminal | Operational |
| 02 | Salarjung Museum | Under Implementation | Heritage Museum Precinct Node | Phase II |
| 03 | Charminar | Under Implementation | Charminar & Mecca Masjid Gateway | Phase II |
| 04 | Shalibanda | Under Implementation | Old City Commercial Hub | Phase II |
| 05 | Falaknuma | Under Implementation | SCR MMTS Railway Station Link | Phase II |
| 06 | Chandrayangutta | Under Implementation Terminal | Proposed Airport Express Line IV Interchange | Phase II |
Hyderabad Metro Green Line Extension (MGBS - Chandrayangutta) Route Map
Hyderabad Metro Green Line Extension (MGBS - Chandrayangutta) Technical Specifications
| Parameter | Value |
|---|---|
| Corridor Status | Under Implementation / Construction Preparatory Works |
| Line Number | Phase II Corridor VI (Green Line Old City Extension) |
| Total Length | 7.5 km |
| Stations Count | 6 Stations |
| Corridor Type | 100% Elevated Viaduct |
| Operator | Telangana Government / Hyderabad Metro Rail Limited (HMRL) |
| Opened / Est. Opening | TBD |
| Maximum Design Speed | 80 km/h |
| Track Gauge | Standard Gauge (1435 mm) |
| Electrification System | 25kV 50Hz AC Overhead Catenary (OHE) |
| Primary Depot | No dedicated depot specified |
Hyderabad Metro Green Line Extension (MGBS - Chandrayangutta) Timeline
7.5-km MGBS–Chandrayangutta Corridor VI included in the 76.4-km Phase-II proposal submitted to MoHUA
General Consultant procurement initiated; land acquisition and construction-preparatory works underway
Hyderabad Metro Green Line Extension (MGBS - Chandrayangutta) Economic & Connectivity Impact
Economic Significance
Brings mass rapid transit directly into the densely populated Old City of Hyderabad, drastically improving mobility for millions of residents.
Traffic Impact
Relieves extreme traffic congestion along narrow heritage road corridors connecting MGBS, Salarjung Museum, Charminar, Shalibanda, and Falaknuma.
Employment Centres Served
Connects traditional craft, textile, and wholesale commercial markets of Old City directly to Secunderabad and Cyberabad.
Intermodal Connectivity
Provides a key interchange link at Chandrayangutta connecting Old City commuters directly to the Shamshabad Airport Express Line IV.
Impact on Real Estate
Expected to drive commercial urban renewal and structured retail redevelopment along Old City transit nodes.
Hyderabad Metro Green Line Extension (MGBS - Chandrayangutta) Alignment Map & GIS Explorer