Pune HCMTR: Route Map, Cost, Status & Latest Construction Progress

Last Updated: September 2026
StatusPre-construction Planning
Length43.6 km
Open SectionsNone (Proposed)
CompletionTarget: 2028 (State Government Target)
Last UpdatedSeptember 2026

The Pune High Capacity Mass Transit Route (HCMTR), also widely referred to as the Pune HCMTR Project, is a proposed elevated ring highway corridor designed to decongest city traffic in Pune, Maharashtra. The Pune High Capacity Mass Transit Route aims to link major suburbs and integrate seamlessly with the existing and upcoming Pune Metro networks.

Fast-tracked by the Maharashtra state government, the HCMTR has an estimated cost of ₹12,000 crore (including ₹9,000 crore for construction and ₹3,000 crore for land acquisition). Reviewing the Pune HCMTR Latest News and Pune HCMTR Construction Update reveals that the corridor features double-decker elevated designs in overlapping segments with the Pune Metro.

FEATURED PARTNER
ADVERTISEMENT

Want Your Brand Featured Here?

Reach thousands of decision-makers and investors searching for infrastructure projects every month.

YOUR BRAND HEREPrime Infrastructure Placement
Total Length43.6 km
Estimated Cost₹12,000 Crore
Implementing AgencyPMC + PMRDA (SPV)
Current StatusPre-construction Planning
Completion TargetTarget: 2028 (State Government Target)
Route Map

Pune HCMTR Route Map & Alignment

View and download the latest Pune HCMTR route map showing the project alignment, major junctions, districts covered and connectivity corridors.

Loading GIS Map Environment...
Project Name📍 Pune HCMTR
Total Length43.6 km
Estimated Cost₹12,000 Crore
Current StatusPre-construction Planning
Project Parameters & Technical Details

Pune HCMTR Technical Specs & Project Parameters

ParameterTechnical Specification
Official Project NamePune High Capacity Mass Transit Route (HCMTR)
Total Corridor LengthApproximately 43.6 km (6-lane elevated ring corridor)
Estimated Cost₹12,000 Crore
Implementing AuthorityPune Municipal Corporation (PMC) & Pune Metropolitan Region Development Authority (PMRDA)
Corridor Width / RoWVaries (Elevated viaduct structure with double-decker Metro integration)
Corridor Start PointBopodi (Circular Loop)
Corridor End PointBopodi (Circular Loop - Complete Ring)
Development ModelSpecial Purpose Vehicle (SPV) model by PMC & PMRDA
Current Project StatusPre-construction Planning
Target CompletionTarget: 2028 (State Government Target)

Corridor Alignment & Engineering Features

Project Status & Fast-Tracking

The project is currently in the Pre-construction Planning stage. Maharashtra Chief Minister Devendra Fadnavis has set a target of 2028 (State Government Target) for the project's completion, establishing a Special Purpose Vehicle (SPV) between Pune Municipal Corporation (PMC) and Pune Metropolitan Region Development Authority (PMRDA) to manage execution and fund raising.

Updated Alignment: 43.6 km vs 36 km

While original planning documents and the initial **Pune HCMTR DPR** referred to approximately 36 km, the updated alignment has been extended to 43.6 km. This updated alignment is designed to optimize the **Pune HCMTR Route** on the official **Pune HCMTR Map**, minimizing private land acquisition while ensuring direct coverage.

Double-Decker Metro Integration

To prevent structural conflicts, the HCMTR is being designed in sync with Maha-Metro routes. Elevated double-decker alignments will be constructed in segments where the road corridor and metro lines share the same right-of-way, reducing the footprint on Pune's congested streets.

Land Acquisition Progress

Approximately 85% of the land required for the 43.6 km elevated route is already available. The state cabinet decided to waive land charges for the 30% of government land required, handing it over free of cost to PMC to expedite civil tendering.

Key Alignment Interchanges & Nodes Covered:
📍 Bopodi📍 Aundh📍 Kothrud📍 Hadapsar📍 Dhanori📍 Bibvewadi
Timeline

Latest Developments

Verified project updates from news sources and official announcements
Video Coverage

Video Updates

Latest drone footage, progress reports, and ground coverage
Project Schedule

Latest Project Updates & Timeline

1987

HCMTR Proposal

The Pune High Capacity Mass Transit Route (HCMTR) ring corridor was first proposed and included in Pune's Development Plan (DP).

2016–2018

Alignment Feasibility

Detailed feasibility report and initial alignment finalisation conducted for a 36-km version of the project.

2026

Fast-Tracking & SPV

Maharashtra Government approved setting up a joint Special Purpose Vehicle (SPV) between PMC and PMRDA, waiving government land charges and updating the length to 43.6 km.

2027

Tendering Stage

Re-tendering process for civil execution packages and alignment adjustment in areas of metro overlap.

2028

Target Completion

Under the fast-tracked timeline, the 43.6 km elevated route is targeted to be fully operational.

General Inquiries

Pune HCMTR FAQs

Related Infrastructure Projects

Enjoy tracking infrastructure projects?

Get monthly updates whenever major Indian infrastructure projects move forward.

✓Project milestones
✓Government approvals
✓Construction progress
✓New project launches
🏛️Visit Maharashtra Dashboard →MH
🗺️Explore All State Dashboards →ALL
📰Read Latest Infrastructure News →LATEST
RELATED
Never miss a project update.

Join the Infracapitalist Newsletter