CORRIDOR DOSSIER INDEX // KANPUR-KABRAI-EXPRESSWAY

Kanpur–Kabrai Greenfield Expressway Route Map & Latest Updates

Last Updated: September 2026
StatusApproved / Land Acquisition Stage
Length112 km
Open SectionsUnder Land Acquisition & DPR Stage
Completion2028
Last UpdatedSeptember 2026
The Kanpur–Kabrai Greenfield Expressway, also known as the Kanpur–Kabrai Highway Project, is a proposed 112 km access-controlled highway connecting Kanpur and Kabrai in Uttar Pradesh. Estimated at ₹7,145 crore, it slashes travel times to under 2 hours.
The Kanpur–Kabrai Greenfield Expressway, also known as the Kanpur–Kabrai Highway Project, is a proposed 112 km access-controlled highway connecting Kanpur and Kabrai in Uttar Pradesh. Estimated at approximately ₹7,145 crore, the Kanpur to Kabrai Expressway is engineered to halve commuting times between Kanpur Nagar and the mineral-rich Bundelkhand belt to under 2 hours, bypassing congested bottlenecks along the existing Kanpur Kabrai Highway corridor.

Developed by the National Highways Authority of India (NHAI), the official Kanpur Kabrai Expressway Route spans across Kanpur Nagar, Kanpur Dehat, Hamirpur, and Mahoba districts. Ongoing pre-construction work focuses on the Kanpur Kabrai Land Acquisition notices and GIS survey alignment details shown on the Kanpur Kabrai Expressway Map. This project also links seamlessly with the Lucknow Kanpur Expressway and Ganga Expressway networks.
FEATURED PARTNER
ADVERTISEMENT

Want Your Brand Featured Here?

Reach thousands of decision-makers and investors searching for infrastructure projects every month.

YOUR BRAND HEREPrime Infrastructure Placement
Total Length112 km
Estimated Cost₹7,145 Cr
Implementing AgencyNHAI
Current StatusApproved / Land Acquisition Stage
Completion Target2028
Route Map

Kanpur–Kabrai Expressway Route Map

View and download the latest kanpur kabrai expressway route map showing the project alignment, major junctions, districts covered and connectivity corridors.

Loading GIS Map Environment...
Project Name📍 kanpur kabrai expressway
Total Length112 km
Estimated Cost₹7,145 Cr
Current StatusApproved / Land Acquisition Stage
Project Parameters & Technical Details

kanpur kabrai expressway Technical Specs & Project Parameters

ParameterTechnical Specification
Official Project NameKanpur–Kabrai Greenfield Expressway Route Map & Latest Updates
Total Corridor Length112 km
Estimated Cost₹7,145 Cr
Implementing AuthorityNHAI
Corridor Width / RoWStandard NHAI access-controlled highway cross-section
Corridor Start PointStart point as per DPR / Alignment plan
Corridor End PointEnd point as per DPR / Alignment plan
Development ModelBOT (Toll) / Item Rate / EPC as per tender specifications
Current Project StatusApproved / Land Acquisition Stage
Target Completion2028

Corridor Alignment & Engineering Features

The Kanpur–Kabrai Greenfield Expressway, also known as the Kanpur–Kabrai Highway Project, is a proposed 112 km access-controlled highway connecting Kanpur and Kabrai in Uttar Pradesh. Estimated at approximately ₹7,145 crore, the Kanpur to Kabrai Expressway is engineered to halve commuting times between Kanpur Nagar and the mineral-rich Bundelkhand belt to under 2 hours, bypassing congested bottlenecks along the existing Kanpur Kabrai Highway corridor.

Developed by the National Highways Authority of India (NHAI), the official Kanpur Kabrai Expressway Route spans across Kanpur Nagar, Kanpur Dehat, Hamirpur, and Mahoba districts. Ongoing pre-construction work focuses on the Kanpur Kabrai Land Acquisition notices and GIS survey alignment details shown on the Kanpur Kabrai Expressway Map. This project also links seamlessly with the Lucknow Kanpur Expressway and Ganga Expressway networks.
Key Alignment Interchanges & Nodes Covered:
📍 Kanpur Nagar📍 Kanpur Dehat📍 Hamirpur📍 Mahoba (Kabrai)
Timeline

Latest Developments

Verified project updates from news sources and official announcements
Video Coverage

Video Updates

Latest drone footage, progress reports, and ground coverage
Project Schedule

Latest Project Updates & Timeline

November 2018

DPR Finalised

Detailed Project Report for ₹4,500 crore project finalised and submitted to the Government of Uttar Pradesh.

March 2019

Foundation Stone Laid

Foundation stone laid down on 7 March by Union Ministers - Rajnath Singh and Nitin Gadkari for this project.

December 2020

National Expressway 6

Lucknow Kanpur Expressway declared as NE 6 on December 15, 2020.

February 2021

Land Acquisition Done

Land acquisition done. Civil engineering work is expected to start in July 2021.

February 2022

Contractor Selection

PNC Infratech emerges as the Lowest Bidder and is selected by NHAI to build and operate both packages under HAM.

October 2025

Greenfield Section Ready

Unnao section is complete with finishing touches done while the work is underway in Lucknow package.

February 2026

85% Progress Reached

The wires shifted and all concrete girders launched with deck slabbing underway in Lucknow package. Overall progress is at 85%.

May 2026

Major Ramps Underway

Major work at couple of Ramps and toll plazas in the Lucknow package is still underway, with overall progress at 99%.

General Inquiries

Kanpur–Kabrai Expressway FAQs

Related Infrastructure Projects

Enjoy tracking infrastructure projects?

Get monthly updates whenever major Indian infrastructure projects move forward.

✓Project milestones
✓Government approvals
✓Construction progress
✓New project launches
🏛️Visit Uttar Pradesh Dashboard →UP
🗺️Explore All State Dashboards →ALL
📰Read Latest Infrastructure News →LATEST
RELATED
Never miss a project update.

Join the Infracapitalist Newsletter