CORRIDOR DOSSIER INDEX // NASHIK-AHILYANAGAR-HIGHWAY

Nashik–Ahilyanagar Greenfield Highway Route Map, NHAI Tender, Cost & Alignment (2026)

Last Updated: September 2026
StatusTendering Active / Bids Closing 30 Sept 2026
Length152 km
Open Sections0 km (Tendering / Pre-construction)
Completion1,095 Days (Period of Work)
Last UpdatedSeptember 2026

The Nashik–Ahilyanagar Greenfield Highway is a 6-lane access-controlled greenfield highway developed by the National Highways Authority of India (NHAI) in Maharashtra. Spanning approximately ~152 km from the NH-60 junction at Adgaon, Nashik (km 138.000) to Ahilyanagar (km 290.000), the project is officially tendered as Ahilyanagar Bypass Package I (NHAI Tender ID: 2026_NHAI_277028_1).

With an NHAI tender value of ₹7,596.33 crore and a 1,095-day construction period, the project is structured under an Item Rate contract within an overall BOT (Toll) framework. It forms the Nashik–Ahilyanagar section of the 374-km Nashik–Solapur–Akkalkot Greenfield Corridor approved by the Union Cabinet / Cabinet Committee on Economic Affairs (CCEA) in December 2025 at an aggregate outlay of ₹19,142 crore.

FEATURED PARTNER
ADVERTISEMENT

Want Your Brand Featured Here?

Reach thousands of decision-makers and investors searching for infrastructure projects every month.

YOUR BRAND HEREPrime Infrastructure Placement
Total Length152 km
Estimated Cost₹7,596.33 Crore (NHAI Tender Value)
Implementing AgencyNational Highways Authority of India (NHAI)
Current StatusTendering Active / Bids Closing 30 Sept 2026
Completion Target1,095 Days (Period of Work)
Route Map

Nashik–Ahilyanagar Greenfield Highway Route Map & Alignment

View and download the latest Nashik–Ahilyanagar Greenfield Highway route map showing the project alignment, major junctions, districts covered and connectivity corridors.

Loading GIS Map Environment...
Project Name📍 Nashik–Ahilyanagar Greenfield Highway
Total Length152 km
Estimated Cost₹7,596.33 Crore (NHAI Tender Value)
Current StatusTendering Active / Bids Closing 30 Sept 2026
Project Parameters & Technical Details

Nashik–Ahilyanagar Greenfield Highway Technical Specs & Project Parameters

ParameterTechnical Specification
Official Project NameNashik–Ahilyanagar Greenfield Highway (Ahilyanagar Bypass Package I)
Total Corridor Length152 km (6-Lane Access-Controlled Greenfield Highway)
Estimated Cost₹7,596.33 Crore (NHAI Tender Value)
Implementing AuthorityNational Highways Authority of India (NHAI)
Corridor Width / RoW6-lane access-controlled greenfield cross-section with paved shoulders & utility corridor
Corridor Start PointJunction with NH-60 at Adgaon, Nashik (km 138.000)
Corridor End PointAhilyanagar (km 290.000)
Development ModelBOT (Toll) — Item Rate Tender under NHAI
Current Project StatusTendering Active / Bids Closing 30 Sept 2026
Target Completion1,095 Days (Period of Work)

Corridor Alignment & Engineering Features

Corridor Alignment & Chainage Specs

The greenfield alignment initiates at the junction with NH-60 at Adgaon in Nashik (km 138.000) and traverses south-eastwards across Nashik and Ahilyanagar (Ahmednagar) districts, bypassing congested urban stretches before integrating at Ahilyanagar (km 290.000). The approved Nashik–Solapur–Akkalkot Greenfield Corridor features a design speed of 100 km/h, with an expected average vehicular speed of about 60 km/h.

Union Cabinet Approval & Strategic Impact

Sanctioned by the Union Cabinet / CCEA in December 2025 as part of the 374-km Nashik–Solapur–Akkalkot Greenfield Corridor (aggregate cost ₹19,142 crore), the overall Nashik–Akkalkot corridor is expected to reduce travel time from about 31 hours to about 17 hours, unlocking high-speed industrial and agricultural mobility between North and South Maharashtra.

NHAI Tender & BOT Scope

NHAI issued open competitive bids under Tender ID 2026_NHAI_277028_1 (Ref: NHAI/MH/ Nashik-Ahilyanagar/ PkgI) for 6-lane access-controlled greenfield highway construction with an NHAI tender value of ₹7,596.33 crore and a 1,095-day period of work. The Package-I scope operates within a BOT (Toll) framework, with bids scheduled to close on 30 September 2026 and technical bid opening on 1 October 2026.

Broader Connectivity & Industrial Hubs

As the Nashik–Ahilyanagar section of the 374-km corridor, this greenfield highway establishes rapid access between the major manufacturing and agro-processing clusters of Nashik, Sinnar, and the Ahilyanagar district, seamlessly linking with the southern Package II alignment toward Solapur and Akkalkot.

Key Alignment Interchanges & Nodes Covered:
📍 Adgaon (Nashik NH-60 Junction)📍 Sinnar Region📍 Sangamner / Shrirampur Border Area📍 Rahuri Region📍 Ahilyanagar (Ahmednagar) Bypass (km 290.000)
Timeline

Latest Nashik–Ahilyanagar Highway News

Verified project updates from news sources and official announcements
Video Coverage

Video Updates

Latest drone footage, progress reports, and ground coverage
Project Schedule

Nashik–Ahilyanagar Highway Timeline & Milestones

Dec 2025

Cabinet / CCEA Sanction

The Cabinet Committee on Economic Affairs (CCEA) approved the 374-km Nashik–Solapur–Akkalkot 6-lane greenfield economic corridor at an estimated cost of ₹19,142 crore.

May 2026

NHAI Package I Tender Issued

NHAI issued open bids under Tender ID 2026_NHAI_277028_1 (Ref: NHAI/MH/ Nashik-Ahilyanagar/ PkgI) on 9 May 2026 for construction of the 6-lane greenfield highway from Adgaon/Nashik (km 138.000) to Ahilyanagar (km 290.000) with a ₹7,596.33 crore tender value and 1,095-day work period.

30 Sept 2026

Bid Submission Deadline

Scheduled closing deadline for submission of technical and commercial bids under the active NHAI Package I tender.

1 Oct 2026

Technical Bid Opening

Scheduled opening of technical bids submitted for the Nashik–Ahilyanagar 6-lane greenfield highway contract.

General Inquiries

Nashik–Ahilyanagar Greenfield Highway FAQs

Related Infrastructure Projects

Enjoy tracking infrastructure projects?

Get monthly updates whenever major Indian infrastructure projects move forward.

✓Project milestones
✓Government approvals
✓Construction progress
✓New project launches
🏛️Visit Maharashtra Dashboard →MH
🗺️Explore All State Dashboards →ALL
📰Read Latest Infrastructure News →LATEST
RELATED
Never miss a project update.

Join the Infracapitalist Newsletter