CORRIDOR DOSSIER INDEX // TALEGAON-TO-CHAKAN-TO-SHIKRAPUR-ELEVATED-HIGHWAY

Talegaon-Chakan-Shikrapur Elevated Highway Route Map, Cost & Latest Update (2026)

Last Updated: September 2026
StatusUnder Construction / DFBOT Model
Length53.2 km | MSIDC
Open SectionsConstruction Stage
Completion4 years from commencement
Last UpdatedSeptember 2026
The Talegaon to Chakan to Shikrapur Highway is a 53.2 km NH-548D corridor featuring a 4-lane elevated road and parallel 4-lane at-grade road from Talegaon to Chakan, plus a 4-lane at-grade highway from Chakan to Shikrapur, under MSIDC.

The Talegaon to Chakan to Shikrapur Elevated Highway is a major infrastructure corridor spanning a total length of 53.2 km along NH-548D in Pune district, Maharashtra. With an approved project cost of ~₹4,200 crore (administrative sanction ₹3,923.89 crore; earlier MSIDC estimate ₹6,150 crore), the corridor features a 4-lane elevated road + parallel 4-lane at-grade road from Talegaon to Chakan, plus a 4-lane at-grade highway from Chakan to Shikrapur.

Designed to eliminate severe industrial traffic bottlenecks connecting the Talegaon MIDC, Chakan Auto Hub, and Shikrapur manufacturing hubs—which currently handle an intense traffic load of 40,839 PCU/day (Passenger Car Units per day)—the project is implemented by the Maharashtra State Infrastructure Development Corporation (MSIDC) / Government of Maharashtra under the DFBOT Model with a target completion timeline of 4 years from commencement (LoA issued on 29 April 2026 and civil work launched on the 26.30 km Talegaon–Chakan elevated stretch following the July 2026 foundation ceremony). Land acquisition requirements span approximately 56 hectares (with 38.79 ha listed in initial MSIDC estimates), and tolling will follow standard NHAI policy.

FEATURED PARTNER
ADVERTISEMENT

Want Your Brand Featured Here?

Reach thousands of decision-makers and investors searching for infrastructure projects every month.

YOUR BRAND HEREPrime Infrastructure Placement
Total Length53.2 km | MSIDC
Estimated Cost~₹4,200 Crore (Approved Cost; ₹6,150 Crore original estimate)
Implementing AgencyMSIDC / Government of Maharashtra
Current StatusUnder Construction / DFBOT Model
Completion Target4 years from commencement
Route Map

Talegaon to Chakan to Shikrapur Elevated Highway Route Map & Alignment

View and download the latest Talegaon to Chakan to Shikrapur Elevated Highway route map showing the project alignment, major junctions, districts covered and connectivity corridors.

Loading GIS Map Environment...
Project Name📍 Talegaon to Chakan to Shikrapur Elevated Highway
Total Length53.2 km | MSIDC
Estimated Cost~₹4,200 Crore (Approved Cost; ₹6,150 Crore original estimate)
Current StatusUnder Construction / DFBOT Model
Project Parameters & Technical Details

Talegaon to Chakan to Shikrapur Elevated Highway Technical Specs & Project Parameters

ParameterTechnical Specification
Official Project NameTalegaon-Chakan-Shikrapur Elevated Highway Route Map, Cost & Latest Update (2026)
Total Corridor Length53.2 km | MSIDC
Estimated Cost~₹4,200 Crore (Approved Cost; ₹6,150 Crore original estimate)
Implementing AuthorityMSIDC / Government of Maharashtra
Corridor Width / RoWTalegaon–Chakan: 4-lane elevated + 4-lane at-grade; Chakan–Shikrapur: 4-lane at-grade (38.79 ha original / ~56 ha expanded acquisition requirement)
Corridor Start PointTalegaon Dabhade (Pune District)
Corridor End PointShikrapur (via Chakan / Pune District)
Development ModelMSIDC Execution (NHAI Toll Policy)
Current Project StatusUnder Construction / DFBOT Model
Target Completion4 years from commencement

Corridor Alignment & Engineering Features

Project Alignment & Configuration Breakdown

Connecting Talegaon, Chakan, and Shikrapur along NH-548D, this 53.2 km highway serves as the primary East-West industrial artery of Pune district, linking the Mumbai–Pune Expressway with the Pune–Nashik (NH-60) and Pune–Ahmednagar (NH-753F) corridors. The approved scheme features a 4-lane elevated road and parallel 4-lane at-grade road between Talegaon and Chakan, followed by a 4-lane at-grade surface highway between Chakan and Shikrapur to seamlessly segregate high-speed regional freight from local industrial traffic.

DPR Status & MSIDC Implementation

The Detailed Project Report (DPR) prepared by NHAI was handed over to MSIDC. Following the Letter of Award (LoA) on 29 April 2026 and foundation stone ceremony on 18 July 2026, active civil construction is underway under MSIDC / Government of Maharashtra under the DFBOT Model with a 4-year completion target window.

Land Acquisition & Tolling Framework

Initial MSIDC project estimates cited 38.79 hectares of land acquisition, while current project planning indicates acquisition requirements expanding to approximately 56 hectares. User fee collection and tolling will follow standard NHAI toll policy regulations.

Key Alignment Interchanges & Nodes Covered:
📍 Banashankari / Srinagar area📍 Hosakerehalli vicinity📍 Kengeri area📍 Sompura area
Timeline

Latest Developments

Verified project updates from news sources and official announcements
Video Coverage

Video Updates

Latest drone footage, progress reports, and ground coverage
Project Schedule

Latest Project Updates & Timeline

March 2024 / 2025

NHAI DPR Handover to MSIDC

Detailed Project Report prepared by NHAI was officially handed over to MSIDC for state-level execution as part of Maharashtra's mega infrastructure package.

April 2026

Administrative Approval & Scope Corrigendum

Government of Maharashtra issued administrative sanction for ₹3,923.89 crore (with overall project reporting ~₹4,200 crore) under DFBOT model.

29 April 2026

Letter of Award Issued

Tender evaluation completed and Letter of Award (LoA) issued to selected concessionaire under DFBOT model.

July 2026

Foundation Ceremony & Civil Works

Foundation stone laid on 18 July 2026 and civil construction commenced on the 26.30 km Talegaon–Chakan 4-lane elevated corridor section.

4 Years (Target ~2030)

Target Completion Window

Project scheduled for full completion within 4 years from work commencement, delivering the 53.2 km NH-548D capacity upgrade.

General Inquiries

Talegaon to Chakan to Shikrapur Elevated Highway FAQs

Related Infrastructure Projects

Enjoy tracking infrastructure projects?

Get monthly updates whenever major Indian infrastructure projects move forward.

✓Project milestones
✓Government approvals
✓Construction progress
✓New project launches
🏛️Visit Maharashtra Dashboard →MH
🗺️Explore All State Dashboards →ALL
📰Read Latest Infrastructure News →LATEST
RELATED
Never miss a project update.

Join the Infracapitalist Newsletter