Agra Metro: Route Map, Lines, Stations & Latest Updates (2026) (आगरा मेट्रो)

Last Updated: August 2026

Agra Metro Rail is a mass rapid transit system serving the historical city of Agra, Uttar Pradesh. Implemented by Uttar Pradesh Metro Rail Corporation Limited (UPMRC), a 50:50 joint venture of the Government of India and the Government of Uttar Pradesh, the 29.4 km Phase 1 network comprises two corridors connecting key urban nodes, railway stations, and heritage areas.

System Quick Facts
Opened6 March 2024 (Priority Corridor)
OperatorUttar Pradesh Metro Rail Corporation Limited (UPMRC)
Network TypeRapid Transit (Elevated & Underground)
GaugeStandard Gauge (1435 mm)
Electrification750V DC Third Rail
Phase 1 Network Length29.4 km (2 Corridors)
Rolling StockAlstom Movia Metro trainsets
Current Status6 km operational; remaining Phase 1 sections under construction. The Taj East Gate–Mankameshwar 6 km section has been operational since 6 March 2024.
Priority Operational Corridor6 km
Under Construction23.4 km
Approved Corridors29.4 km
Total Planned Stations27 Stations
Underground Stations7 Stations
Project Investment₹8,379.62 crore
Operational CorridorsTaj East Gate–Mankameshwar (6 km)
1 Priority Section
Under ConstructionLine 1 Balance & Line 2 Active Construction
2 Corridors
Approved NetworkFull Union Cabinet Phase 1 Approval (29.4 km)
2 Corridors
Network Corridors

Agra Metro Phase 1 Corridors

Uttar Pradesh Metro Rail Corporation Limited (UPMRC), a 50:50 joint venture of the Government of India and the Government of Uttar Pradesh, is constructing the 29.4 km Agra Metro Phase 1 network across two key corridors:

Line 1 (Operational Section): Taj East Gate to Mankameshwar

6.0 km operational priority section with 6 stations (3 elevated, 3 underground) open to the public since 6 March 2024.

Line 1 (Under Construction): Mankameshwar to Sikandra

7.7 km under-construction western extension toward Sikandra across 8 stations (4 underground: Medical College, Raja Ki Mandi, RBS College, Ambedkar University; 4 elevated: Shastri Nagar, ISBT, Guru ka Taal, Sikandra).

Line 2 (Under Construction): Agra Cantt to Kalindi Vihar

15.7 km active under-construction corridor connecting Agra Cantt to Kalindi Vihar across 14 elevated stations.

Geospatial Alignment

Agra Metro Route Map & Network Map

Loading GIS Map Environment...
Network Corridors

Agra Metro Lines & Stations

Agra Metro Phase 1 Corridors

3 Listed Corridors & Sections
Technical & Operational Overview

Agra Metro Network Statistics

Phase 1 Network29.4 km
Operational Section6 km Priority
Total Planned Stations27 Stations
Underground Stations7 Stations
OperatorUPMRC
Project Cost₹8,379.62 crore
Development Roadmap

Agra Metro Network Timeline

2019

Union Cabinet Approval

Union Cabinet approved Agra Metro Phase 1 (29.4 km, 27 stations, ₹8,379.62 crore).

2020

Construction Work Commenced

Construction work commenced on Phase 1 corridors.

6 March 2024

Priority Corridor Inaugurated

Taj East Gate–Mankameshwar 6 km priority corridor inaugurated and passenger services commenced.

2024–2026

Ongoing Phase 1 Construction

Construction continued on the remaining Phase 1 corridors.

Intermodal Integration

Connectivity

Major Railway Terminals

Provides direct multi-modal transit links to Agra Cantt Railway Station (Line 2 / Corridor 2), Agra Fort Railway Station (Line 1 underground), and Raja Ki Mandi Railway Station (Line 1 underground).

Bus Terminals & Highways

Integrates with ISBT Agra (Inter-State Bus Terminal) on Line 1 and provides feeder connections toward Yamuna Expressway, NH-19 (Delhi-Agra Highway), and Idgah Bus Stand.

UNESCO Heritage Sites

Serves World Heritage monuments including Taj Mahal (via Taj East Gate & Taj Mahal underground stations), Agra Fort, and Mankameshwar Mandir in the historical city core.

Educational & Civic Hubs

Links key educational & civic centers including Agra College (multi-line interchange), SN Medical College, RBS College, District Collectorate, and Sanjay Place CBD.

Strategic Impact

Strategic Impact of Agra Metro

TTZ Environmental & Monument Protection

Deploys 750V DC electric trains to replace fossil-fuel vehicular traffic within the Taj Trapezium Zone (TTZ), drastically reducing SPM and SO2 emissions that degrade the white marble of UNESCO heritage monuments.

Tourist Transit & De-Congestion

Seamlessly connects over 7 million annual tourists arriving at Agra Cantt and Agra Fort railway terminals directly to hotel corridors along Fatehabad Road, bypassing choked city roads.

Economic & Commuter Mobility

Transforms daily commuting for over 1.6 million residents by cutting peak transit times between Taj East Gate and Sikandra from over 60 minutes to just 22 minutes while energizing commercial hubs across MG Road and Sanjay Place.

Real-time Briefings

Latest Agra Metro News & Updates

Answers

Frequently Asked Questions

Enjoy tracking infrastructure projects?

Get monthly updates whenever major Indian infrastructure projects move forward.

Project milestones
Government approvals
Construction progress
New project launches
Found incorrect data?
Never miss a project update.

Join the Infracapitalist Newsletter