Home/Metro/Kanpur Metro Rail Network
METRO DOSSIER INDEX // KANPUR-METRO-NETWORK

Kanpur Metro Route Map 2026: Stations, Timings, Fare, Phase 1 & Latest News (कानपुर मेट्रो)

Last Updated: 2026 • Official UPMRC & MoHUA Project Data

Kanpur Metro Rail is a modern mass rapid transit system serving the industrial and academic metropolis of Kanpur, Uttar Pradesh. Implemented by Uttar Pradesh Metro Rail Corporation Limited (UPMRC), a 50:50 joint venture of the Government of India and the Government of Uttar Pradesh, the 32.385 km Phase 1 network comprises two key corridors connecting premier universities, medical centers, railway terminals, and dense residential suburbs.

System Quick Facts
Commissioning28 December 2021 (Priority) / 30 May 2025 (IIT Kanpur to Kanpur Central)
OperatorUttar Pradesh Metro Rail Corporation Limited (UPMRC)
Network TypeRapid Transit (Elevated Viaducts & Underground Twin Tunnels)
GaugeStandard Gauge (1435 mm)
Electrification750V DC Third Rail (Bottom Contact)
Technical SpeedMaximum Design Speed: 90 km/h | Operating Speed: 80 km/h
Rolling StockAlstom Movia 3-Car Stainless Steel EMUs (39 trainsets / 117 coaches)
Signalling SystemAlstom CITYFLO 650 CBTC with Automatic Train Operation (ATO)
Operational Section15.0 km / 14 stations operational from IIT Kanpur to Kanpur Central
Remaining ScopeApproximately 17.3 km remaining under construction / commissioning
Total Planned Stations29 Stations (19 Elevated, 10 Underground)
Primary DepotsIIT Polytechnic Depot (Line 1) & CSA Agriculture University Depot (Line 2)
Current Status15.0 km / 14 stations operational from IIT Kanpur to Kanpur Central; approximately 17.3 km remaining. Passenger services operate from IIT Kanpur to Kanpur Central, with the Kanpur Central–Naubasta section awaiting commencement of passenger services and Line 2 (CSA–Barra-8) under active construction.
Operational Section15.0 km (14 Stations)
Remaining Scope~17.3 km Remaining
Approved Phase 1 Network32.385 km (29 Stations)
Underground Sections10 Underground Stations
Project Outlay₹11,076.48 Cr
Fare Range₹10–₹40
Operational CorridorIIT Kanpur to Kanpur Central (Operational passenger service)
15.0 km (14 Stations)
Under Construction / CommissioningKanpur Central–Naubasta (awaiting services) & Line 2 (CSA–Barra-8)
Approx. 17.3 km
Approved Phase 1 NetworkFull Union Cabinet Phase 1 Master Plan
32.385 km (29 Stations)
Network Corridors

Kanpur Metro Phase 1 Corridors

Uttar Pradesh Metro Rail Corporation Limited (UPMRC), a 50:50 joint venture of the Government of India and the Government of Uttar Pradesh, is implementing the 32.385 km Kanpur Metro Phase 1 network across two high-density corridors:

Line 1 / Corridor 1 (Orange Line): IIT Kanpur to Naubasta (23.785 km, 21 Stations: 14 Elevated + 7 Underground)

North-South trunk arterial corridor linking the premier academic hub of IIT Kanpur with the southern residential hub of Naubasta. Passenger services operate across 15.0 km and 14 stations from IIT Kanpur to Kanpur Central (IIT Kanpur, Kalyanpur, SPM Hospital, Vishwavidyalaya, Gurudev Chauraha, Geeta Nagar, Rawatpur, LLR Hospital, Moti Jheel, Chunniganj, Naveen Market, Bada Chauraha, Nayaganj, and Kanpur Central). The remaining section to Naubasta (including Jhakarkati Bus Terminal, Transport Nagar, Baradevi, Kidwai Nagar, Vasant Vihar, Baudh Nagar, and Naubasta) has completed statutory CMRS safety inspection and is awaiting commencement of passenger services.

Line 2 / Corridor 2 (Blue Line): CSA Agriculture University to Barra-8 (8.60 km, 8 Stations: 5 Elevated + 3 Underground)

East-West connectivity corridor connecting Chandra Shekhar Azad (CSA) Agriculture University to Barra-8 across 8 stations (3 underground: CSA Agriculture University, Rawatpur future interchange, Kakadeo; and 5 elevated: Double Pulia, Vijay Nagar, Shastri Chowk, Barra-7, Barra-8). Currently under active construction.

Geospatial Alignment

Kanpur Metro Route Map & Network Map

Loading GIS Map Environment...
Network Corridors

Kanpur Metro Lines & Stations

Kanpur Metro Phase 1 Corridors

2 Listed Corridors
Technical & Operational Overview

Kanpur Metro Network Statistics

Phase 1 Network32.385 km (2 Corridors)
Operational Section15.0 km (14 Stations)
Remaining Scope~17.3 km Remaining
Underground Stations10 Stations (Phase 1)
OperatorUPMRC
Total Project Cost₹11,076.48 Cr
Development Roadmap

Kanpur Metro Rail Network Timeline

28 Feb 2019

Union Cabinet Approval

Union Cabinet approved the 32.385-km Kanpur Metro Rail Phase 1 project across two corridors at an estimated cost of ₹11,076.48 crore.

15 Nov 2019

Priority Corridor Construction Launch

Civil piling and viaduct erection commenced on the 8.98-km Priority Section from IIT Kanpur to Moti Jheel.

28 Dec 2021

Priority Section Inaugurated

Prime Minister Narendra Modi inaugurated the 8.98-km elevated Priority Corridor (9 stations from IIT Kanpur to Moti Jheel) for commercial passenger operations.

30 May 2025

Services Extended to Kanpur Central

Passenger operations extended underground to Kanpur Central across 14 stations covering 15.0 km.

June 2026

CMRS Inspection of Naubasta Section

Statutory CMRS safety inspection completed for the Kanpur Central–Naubasta section, which is awaiting commencement of passenger services.

Underway

Line 2 (Blue Line) Construction

Construction of Corridor 2 connecting CSA Agriculture University to Barra-8 across 8 stations with future interchange at Rawatpur.

Intermodal Integration

Connectivity

Kanpur Central Railway Station (NCR)

Direct subterranean connection via underground metro station to Kanpur Central (CNB), one of Indian Railways' highest-volume junction terminals along the Delhi–Howrah mainline.

Jhakarkati Inter-State Bus Terminal (ISBT)

Planned multi-modal interchange connecting Jhakarkati ISBT with the Kanpur Metro’s Naubasta extension.

Rawatpur Multi-Modal Junction (Future Interchange)

Planned future interchange station connecting Line 1 (Orange Line) with Line 2 (Blue Line) alongside interchange access to Rawatpur Railway Station.

Premier Academic & Healthcare Hubs

Fast, congestion-free access to IIT Kanpur, CSJM University, Harcourt Butler Technical University (HBTU), CSA University, GSVM Medical College, and LLR Hospital (Hallet).

Strategic Impact

Strategic Impact of Kanpur Metro

Industrial & Urban De-Congestion

Replaces high-emission vehicular, bus, and three-wheeler traffic along the heavily congested Grand Trunk (GT) Road and Mall Road corridors with an eco-friendly 750V DC electric mass transit system.

Multi-Modal Intercity Transit Velocity

Connects IIT Kanpur and Kalyanpur directly to Kanpur Central Railway Station with reliable, high-speed, and congestion-free rapid transit.

Economic Revitalisation & Air Quality Improvement

Significantly cuts particulate matter (PM2.5 and PM10) emissions in one of India's major industrial hubs while enhancing commercial footfall in historical market centers like Bada Chauraha and Naveen Market.

Real-time Briefings

Latest Kanpur Metro News & Updates

Answers

Frequently Asked Questions

Enjoy tracking infrastructure projects?

Get monthly updates whenever major Indian infrastructure projects move forward.

✓Project milestones
✓Government approvals
✓Construction progress
✓New project launches
🏛️Visit Uttar Pradesh Dashboard →UP
🗺️Explore All State Dashboards →ALL
📰Read Latest Infrastructure News →LATEST
RELATED
Never miss a project update.

Join the Infracapitalist Newsletter