Kolkata Metro Line 4 (Yellow Line — Under Construction Section: Jai Hind Airport ↔ Michael Nagar)

Under Construction📏 2.06 km Under Construction Route🚉 2 Planned Underground Stations (Birati and Michael Nagar) Stations🗓 Target Opening: 2027🏢 Metro Railway, Kolkata (Owner: Indian Railways / RVNL)

Kolkata Metro Line 4 (Yellow Line - Under Construction Segment) spans 2.06 km across 2 underground stations (Birati and Michael Nagar). Extending from the operational Jai Hind (NSCBI Airport) subterranean terminal, this underground section passes through Birati to Michael Nagar, bypassing heavy surface encroachments and airport runway obstruction zones along Jessore Road.

FEATURED PARTNER
ADVERTISEMENT

Want Your Brand Featured Here?

Reach thousands of decision-makers and investors searching for infrastructure projects every month.

YOUR BRAND HEREPrime Infrastructure Placement
Kolkata Metro Yellow Line Economics

Kolkata Metro Yellow Line Economics

Total InvestmentUnderground Revision Modification Cost ₹1,615 Cr
Primary BackersMinistry of Railways (Government of India)
Operator / ModelMetro Railway, Kolkata (Owner: Indian Railways / RVNL)
Target Opening

Expected Completion Date

StatusUnder Construction
Target Opening DateTarget Opening: 2027
Station list

Kolkata Metro Yellow Line Stations

#StationTypeInterchange / ConnectionOpened
01
Jai Hind
Underground Operational HubNSCBI Airport Terminal & Line 6 Orange Line Interchange25 August 2025
02
Birati
Underground (Under Construction)Birati Suburb & Jessore Road Junction NodeTarget 2027
03
Michael Nagar
Underground (Under Construction)Michael Nagar Terminal & Barasat Alignment ShaftTarget 2027
Geospatial Alignment

Jai Hind Airport ↔ Michael Nagar Underground Alignment Map

Loading GIS Map Environment...
Specs sheet

Kolkata Metro Yellow Line Technical Specifications

ParameterValue
Corridor StatusUnder Construction
Line NumberLine 4 (Yellow Line)
Total Length2.06 km Under Construction Route
Stations Count2 Planned Underground Stations (Birati and Michael Nagar)
Corridor TypeUnderground Cut-and-Cover Tunneling & TBM Shaft Drive
OperatorMetro Railway, Kolkata (Owner: Indian Railways / RVNL)
Opened / Est. OpeningTarget Opening: 2027
Maximum Design Speed80 km/h
Track GaugeBroad Gauge (1,676 mm / 5 ft 6 in)
Electrification System750V DC Third Rail
Primary DepotNoapara Metro Depot
Chronological Milestones

Kolkata Metro Yellow Line Timeline

June 2019

Railway Board sanctioned ₹1,615 Cr material modification converting Airport–Michael Nagar section underground.

2020

Airports Authority of India (AAI) shifted fuel tanks, utility buildings, and radar cables for underground tunneling.

February 2021

Prime Minister Narendra Modi approved underground cut-and-cover method to prevent eviction of local families along Jessore Road.

25 August 2025

Operational Yellow Line to Jai Hind Airport commissioned; active civil works continued towards Birati and Michael Nagar.

Target 2027

Targeted completion of underground tunneling and commissioning of Birati and Michael Nagar metro stations.

Proprietary analytics

Yellow Line Airport Extension & Northern Suburban Connectivity

Economic Significance

Provides underground high-capacity transit connecting NSCBI Airport directly to dense northern suburban residential zones at Birati and Michael Nagar.

Traffic Impact

Bypasses massive traffic gridlocks on Jessore Road and National Highway 12 (NH-12).

Employment Centres Served

Enables fast daily commute for airport staff, cargo logistics workers, and North 24 Parganas suburban residents.

Intermodal Connectivity

Provides seamless continuous single-seat ride from Birati and Michael Nagar into Noapara and Central Kolkata.

Impact on Real Estate

Sparked commercial redevelopment and residential housing demand in Birati and Michael Nagar.

Geospatial Explorer

Kolkata Metro Yellow Line Alignment Map & GIS Explorer

Corridor Type Breakdown2.06 km Underground Tunnels (2 Stations)
Viaduct LengthN/A (Full 2.06 km section is underground)
Tunnel Length2.06 km Underground Cut-and-Cover Tunnels
River CrossingsBagjola Canal Underground Culvert Drive
Major Bridges / CrossingsN/A
Primary DepotNoapara Metro Depot
Answers

Frequently Asked Questions

Enjoy tracking infrastructure projects?

Get monthly updates whenever major Indian infrastructure projects move forward.

Project milestones
Government approvals
Construction progress
New project launches
Found incorrect data?
Never miss a project update.

Join the Infracapitalist Newsletter